Texas Black looks like mulch and installs like mulch. It's 4 times the material and 5 times the weight, and priced by feel you're making 10 points less than you think.

$275/CY
sell
$150/CY
rock
$23/hr
wage
1.35
burden
$31/hr
burdened

What this one covers

  1. 1

    The ceiling: rock is 55% of the price, so 45% is the most that exists. 50% was never on the table.

  2. 2

    What a real crew does with 2,700 pounds a yard: 1.75 man-hours, which is 26%, off the bottom of your own table.

  3. 3

    The levers, and why this is the first material where buying a machine is the honest answer instead of pushing the crew.

The Debrief

The Decorative Gravel sheet, talked through. 33 minutes.

Every line on the sheet, in order, for the drive to the job: the numbers at the top, what the margin turns into in man-hours, the crew table, and which lever is worth pulling. The video is for seeing the sheet filled in; this is for hearing it argued.

The hosts are AI, made with Google NotebookLM from the script and sheets. The numbers are the sheet's. If the two ever disagree, the sheet wins.

The sheets

Blank sheet

Print it and fill it in with your own numbers while you watch. Letter, landscape.

Download

Filled sheet

The worked example from the video, every number written in. The answer key.

Download

Calculator

The same math as a Google Sheet. Opens a copy in your own Drive. Change the yellow cells, everything else recalculates.

Open ↗

No Google account? View it read-only and use File → Download to take it into Excel.

Texas Black. $275 a yard installed, and the rock costs you $150. Here is the trap on decorative gravel. It looks like mulch. Same wheelbarrow, same rake, same crew of 2, same beds. So it gets priced like mulch with a bigger material line. It is not mulch. The material costs nearly 4 times as much, and a yard of it weighs about 5 times as much. A contractor barrow you would fill to the brim with mulch, you fill maybe a third of the way with gravel, or nobody is lifting it. Five or six trips a yard becomes 13 or 14. If you priced it by feel, you are making about 10 points less than you think, and this page shows where it goes. Texas Black, black star, whatever your yard calls it. The rock changes, the math does not.

The numbers this sheet uses

These are mine, measured on my own jobs in Central Texas. Your rock might be $120, might be $190. Use your number. Two weights to carry around with the prices, because they explain the rest of the page: a yard of hardwood mulch is about 500 pounds, and a yard of this rock is about 2,700. Say about, because it moves with moisture and stone size. Fabric, edge restraint, base prep and the over-order are not in this number. They are separate lines, and they should be.

Sell price to the customer
$275 a cubic yard, installed
What the rock costs
$150 a cubic yard, delivered
What the crew is paid
$23 an hour, average
The burden
1.35
What an hour of labor costs
$31, the wage times the burden

The ceiling

Divide the rock by the price before anybody picks up a shovel. The $150 over the $275 is 54.5%. Your rock is 55% of what you charge. On hardwood mulch it is about a third. One minus that is 45.5%, which is $125 a yard, and that is the most gross profit that exists on a yard of Texas Black. That is if the rock spreads itself. So if your target on this is 50%, it does not exist. Not at $275. Not at any speed.

The three columns on this sheet start higher than the mulch sheet did, because that is where people think gravel lives: 30%, 35% and 40%. At 30%, $82.50 of gross profit, $192.50 of allowable cost, and $42.50 left for labor. That is 1.37 man-hours a yard. At 35%, $96.25, $178.75, $28.75 for labor, 0.93 man-hours. At 40%, $110 of gross profit, $165 allowable, and $15 is the entire labor budget for a yard. That is 0.48 man-hours. Twenty-nine minutes.

One person, 29 minutes, to move a cubic yard of black star from the pile to the bed and rake it out. A yard of it is about 2,700 pounds. So in 29 minutes, one person is moving better than a ton and a quarter by hand and finishing it. That is not a stretch goal. That is not a hustle problem. That number is not real. The 1.37, an hour and 20 minutes a yard, is real. And an hour and 20 minutes a yard is 30% gross profit, not 40.

Rock is 55% of the price. 45% is the most that exists, and 50% was never on the table.

The real pace

Forget what you want to make. What happens when a crew of 2 spreads black star with wheelbarrows, normal residential access, a walk from the driveway to the bed, is 1.75 man-hours a yard. That is our number. The trade puts hand-spread gravel anywhere from an hour to two a yard, so it is the top of the range, and it is the one I would bid.

Run it down. The 1.75 man-hours at $31 is $54.25 of labor. Add the $150 of rock and the yard costs $204.25. The $275 price minus $204.25 is $70.75 of gross profit, which is 25.7%. Look where that lands. It is not the 40% column. It is not the 35% column. It is not even the 30% column. Your actual margin on Texas Black falls off the bottom of your own table. And to make 35% at 1.75 man-hours, the $204.25 divided by 0.65 is $314 a yard. Not $275.

The crew table turns the pace into a day, the same way it did on mulch and sod. A crew of 2 for 8 hours is 16 man-hours, over 1.75, about 9 yards. A crew of 3 is 24 man-hours, 13.5 yards. A crew of 4, 18. A crew of 5, 23 on paper, and read the footnote first. Everybody queues at one pile. On gravel that is worse than anything else you install, because the pile is the bottleneck and the barrow is heavy. The fifth person is not spreading. They are waiting their turn at the same shovel.

Run it backward. A crew of 3 comes home with 10 yards instead of 13.5. The 24 man-hours over 10 yards is 2.4 man-hours a yard, which is $74.40 of labor on a yard you budgeted at $54.25. Gross profit is $50.60, and that is 18%. The price never moved. On gravel, that happens on the first hot day with a long carry.

You priced it for 35%. A real crew with wheelbarrows runs 1.75 man-hours a yard, and that is 26%, off the bottom of your own table.

Which lever pays, and the machine

The grid on sheet 3 has the price per yard across the top, the man-hours per yard down the side, and the gross margin in every cell, with $150 of rock and a $31 hour throughout. The circle at $275 and 1.75 is 26% and $70.75. Get the crew 10% faster, 1.75 down to 1.58, and you climb one row to 28% and $76.17. That is $5.42 a yard. Charge 9% more, $300 a yard, and you move one column across to 32% and $95.75. That is $25 a yard. Price beats speed about 5 to 1 on aggregate. To match a 10% raise on speed alone, the crew would have to get about 50% faster.

Now, 50% sounds impossible, and on the materials before this one it is. On this one it is not, and here is why. Your constraint on gravel is not the person. It is the wheelbarrow. You are moving 2,700 pounds a yard in a container that holds about 2 cubic feet of it. That is a material handling problem, and material handling problems get solved with equipment, not encouragement. A power buggy. A skid steer with a bucket. A conveyor on the right site. Any of them can plausibly halve the haul time. This is the first material in the series where buying a machine is the honest answer instead of pushing the crew.

Just do not do both. If you rent the buggy, your man-hours already came down. Charge for the machine or charge for the hours, not both. And look at what is underneath you on the grid. Somebody quotes $225 a yard to win the job. Same rock, same crew, same everything. The 1.75 row at $225 reads 9%, before anybody gets paid overhead. Fifty dollars off your price costs you 17 points, and no machine on earth gives that back.

The constraint on gravel is the barrow, not the person. Material handling problems get solved with equipment, not encouragement.

Job size and the over-order

Two things the sheet cannot show you, and both cost you money on gravel. First, job size. Three yards in a front bed and 20 yards across a whole property are not the same job per yard. Pulling up, tarping the drive, staging the pile, edging, blowing off, loading out: that is the same hour and a half whether you brought 3 yards or 30. On 30 yards it disappears. On 3 yards you just ate the job. That is what a minimum charge is for.

Second, and this one is specific to rock. Aggregate settles and compacts. If you are ordering 10% over to cover it, and you should be, that is $15 a yard of material you are eating unless it is on the quote. On a 20-yard job that is $300 you gave away. Put the over-order on the quote as a line, with the fabric, the edge restraint and the base prep. None of them is in the $275, and a quote that pretends they are is paying for them out of the $70.75.

Where it goes wrong on your job

The 1.75 was measured with wheelbarrows and normal access, and nothing about your site is in it. These are the days that miss it. The pile got dropped at the street and the beds are behind the house, and 13 trips a yard became 13 long ones. It was August and the crew slowed down the way anybody does pushing a loaded barrow up a slope. Five people worked one pile and two of them spent the day waiting. The job was 3 yards and carried the same hour and a half as 30. The rock settled, the crew spread the 10% you ordered over, and the quote only had the 10 yards on it. The fabric and the edge restraint went in because they had to, and nobody wrote a line for them. And the one that costs the most: it was priced like mulch, because it went in like mulch.

One job over budget usually has a story like one of those behind it. Write it down and move on. Five jobs over with no story is your real pace, and then one of three numbers has to move: the price, the pace, or what the rock costs you. On gravel the pace is the one lever where a rental is a real answer. Run the machine on one job and divide the hours again.

What to do with this

Before you price anything by feel, weigh it. Literally. What does a yard of it weigh, and what does a yard of it cost you? Those two numbers tell you almost everything. Then divide the rock by the price for the ceiling, in 10 seconds. Then take the last gravel job you ran, the yards from the invoice and the crew's hours from your foreman, and divide. Find that row on the sheet and read across. If the number surprises you, watch the episode and price the next one with the barrow in mind. If it does not, you have lost 10 minutes.

Decorative gravel pricing questions

How much does it cost to install a yard of decorative gravel?

On this sheet, $150 of rock plus 1.75 man-hours at a $31 burdened hour, $204.25 in cost against a $275 sell price, before overhead. That is $70.75 of gross profit, 26%. Fabric, edge restraint, base prep and the over-order are separate lines on top of it.

What margin can you make on decorative gravel?

Divide the rock by the price. At $150 and $275 the rock is 55% of the price, so 45.5% is the ceiling, and only if the rock spread itself. A real crew with wheelbarrows makes about 26%. To make 35% at 1.75 man-hours a yard the price has to be $314.

How many yards of gravel can a crew spread in a day?

About 13.5 for a crew of 3 at 1.75 man-hours a yard with wheelbarrows and normal access: 24 man-hours over 1.75. A crew of 2 does about 9. A fifth person mostly waits at the pile. Ten yards from a crew of 3 is 2.4 man-hours a yard and 18%.

Why is pricing gravel like mulch a mistake?

Because it is 4 times the material and 5 times the weight. Rock is 55% of the price where mulch is a third, and a barrow carries a third as much. The same crew, same rake and same beds take 1.75 man-hours a yard instead of 1.23, and the job that looks the same makes about 10 points less.

Should I rent a machine to install gravel?

On gravel, yes, if it halves the haul. The constraint is the wheelbarrow, not the crew, so a power buggy or a skid steer is the one place in this series where speed is worth chasing. Charge for the machine or for the hours it saved, not both.

Do I have to use these prices?

No. These are my prices. Your rock is different, your access is different, your crew is different. The process is the same. Print the blank sheet, put your own numbers in the boxes at the top, and let the rest recalculate. The calculator does the same thing as a Google Sheet.

Prices are mine. Yours are different. The math is the same.

Who made this

Ledge is landscape design-build software. These sheets are the thinking underneath it.

The sheet teaches the math once. Ledge carries it on every job after: the burdened hour, the man-hours the price bought, and what the crew actually did against it, side by side the day the truck is unloaded. The first ten landscape design-build firms run it free, and we make money only when your client pays you. If you want to see it on your own jobs, you talk to me.