The long version

How to price artificial turf installation per square foot

$3.25 of turf is $5.01 of material once the stack goes under it. At 30 square feet a man-hour $11 makes 45%, and one seam costs a small job 3.4 points.

By Edgar Galindo · November 17, 2026 · EP 06 Artificial Turf of Are You Pricing This Right?

Watch the episode and get the sheets

$11 a square foot of artificial turf, and the turf costs you $3.25. That looks like 70%. It isn't. Turf is a system, not a product, and the parts of the system are bought in different units. The turf and the weed barrier by the square foot, the seam tape by the roll, the infill by the bag, the base by the yard. Build all of it on a real 1,500 square foot backyard and the $3.25 becomes $5.01. And for once the news is good. Turf is the one product in it where the price is fine. At a real crew's pace the job makes 45%. The money on turf gets lost in other places: the lines under the turf that never make the quote, a seam on a job that is barely too big for one roll, and a second order that does not match the first.

The numbers this sheet uses

These are mine, measured on my own jobs in Central Texas. Your turf might be $2.20, might be $5.50. Use your number. The $11 is the turf system only: no excavation, no haul-off, no grading. Site prep is its own line on the quote, and it should be. If $11 sounds cheap, it might be. Turf can run $20 a square foot or more depending on the product and the site. The point of this page is how the material builds up and what that leaves for the crew.

Sell price to the customer
$11 a square foot, turf system installed, no site prep
The job
1,500 square feet, a real backyard
What the turf costs
$3.25 a square foot
What the crew is paid
$23 an hour, average
The burden
1.35
What an hour of labor costs
$31, the wage times the burden
The pace
30 square feet per man-hour, a crew of 3 for 2 days

You quoted turf. You installed a system.

Build the yard one layer at a time. The turf is $3.25 a foot, the number you quoted off. Under it goes the base, 4 inches of decomposed granite at $45 a yard. On 1,500 square feet that is 18.5 yards, so you order 19, $855, 57 cents a foot. Under the base, right on the compacted dirt, goes the weed barrier. It comes in 1,000 square foot rolls at $225, you need 1,500, so you buy 2 rolls, $450, 30 cents a foot, and 500 square feet of it goes back in the trailer.

The turf goes down, and then the infill. Silica sand at $20 a bag, 30 square feet a bag, 50 bags, $1,000, 67 cents a foot. Turf comes 15 feet wide, and a 1,500 square foot yard is 38.7 feet on a side, so that is 3 runs and 2 seams, 77 linear feet of seam. A roll of tape at $55 and 2 gallons of glue at $80, 14 cents a foot. About 760 nails at 15 cents, 8 cents a foot.

Add it up and the material is $5.01 a square foot, $7,509 on a $16,500 job. The turf is $3.25 of that. Everything under it, base, barrier, sand, tape, glue and nails, is $1.76. That is 35% of your material cost, in 5 lines that usually never get written down.

Turf, by the square foot
$3.25
Base, 4 inches of decomposed granite, by the yard
$0.57
Weed barrier, by the roll
$0.30
Infill, silica sand, by the bag
$0.67
Seam tape and glue, by the roll and the gallon
$0.14
Nails, by the box
$0.08
The system, a square foot
$5.01
You quoted $3.25 of turf and installed $5.01 of material. The $1.76 under the turf is 35% of the cost, and it is the part that is never on the quote.

The ceiling

Divide the stack by the price before anybody touches a roll. The $5.01 over the $11 is 45.5%. Material is 45.5% of your sell price on turf. One minus that is 54.5%, $5.99 a foot, and that is the most gross profit that exists on this job, if the turf lays itself.

That is a good ceiling. Sod comes in at 39% on its sheet and decorative gravel at 45%. Turf is a good product to sell. The interesting part is not the ceiling. It is what the crew does underneath it.

The real pace, and for once it is good news

Pick three targets: 35%, 40% and 45%. At $11 a foot that is $3.85, $4.40 and $4.95 of gross profit, so the most you can spend is $7.15, $6.60 and $6.05 a foot. Take out the $5.01 of material and $2.14, $1.59 and $1.04 a foot is left for labor. Divide by $31 and you get 0.069, 0.051 and 0.034 man-hours a foot. Nobody can look at 0.034 of an hour and tell you whether it is real. So flip it: 14.5 square feet per man-hour to make 35%, 19.5 for 40%, 29.7 for 45%.

Now what a crew actually does on 1,500 square feet. No excavation, that is billed separately. So this is roll the barrier, spread and compact the base, lay and cut the turf, seam it, nail it, infill it and power broom it. Two days for a crew of 3, 48 man-hours, which is about 30 square feet per man-hour.

The $31 hour over 30 square feet is $1.03 of labor a foot. Add the $5.01 of material and the foot costs $6.04. The $11 price minus $6.04 is $4.96 of gross profit, 45%. And here is a number this series had not been able to write in four episodes. To make 35% on this job, you would only have to charge $9.29. On sod the 35% price came out above the market price. On gravel too. On turf the math says you have $1.71 a foot of room. Your problem on turf is not your price.

At 30 square feet a man-hour, $11 makes 45%, and 35% would only need $9.29. Turf is the one product in the series with room in the price.

Which lever pays

The grid on sheet 3 has the turf cost down the side, the price across the top, and the ceiling in every cell, with the same $1.76 of base, barrier, infill, tape, glue and nails under the turf in every one. The circle at $3.25 and $11 is 55%, $5.99 a foot. Buy your turf 20% cheaper, $3.25 down to $2.60, and you move up one row to 60%, $6.64. That is 65 cents. Charge 14% more, $12.50, and you move one column across to 60%, $7.49. That is $1.50. Twenty percent off your biggest material line got 65 cents. Fourteen percent on the price got $1.50.

Run all three levers at 10%. Ten percent more price is $1.10 a foot. Ten percent cheaper turf is 33 cents. A crew 10% faster is 10 cents. To match a 10% price increase you would have to buy the turf 34% cheaper, or get the crew 107% faster, which is more than free. There is not enough labor in this job to give back.

Here is the rule under all of it. Price beats a cost line by your price divided by that line. The $11 over the $3.25 of turf is 3.4. The $11 over the $1.03 of labor is more than 10. The cheaper a cost line is next to your price, the less it is worth chasing.

Price beats a cost line by your price divided by that line. $11 over $3.25 of turf is 3.4. $11 over $1.03 of labor is more than 10.

The 15-foot line: a bigger job can make less

You do not buy square feet. You buy rolls and bags. On the 1,500 square foot job you bought 2,000 square feet of weed barrier to cover 1,500, and 100 feet of seam tape for a 77-foot seam. On a big job that waste disappears into the total. On a small one it decides the margin.

Shrink the yard to 200 square feet. That is a 14-foot square, and turf comes 15 feet wide, so the whole thing comes off one roll. No seam, no tape, no glue. The material is $5.83 a foot and the ceiling is 47%. Now go to 250 square feet, 15.8 feet on a side. You just crossed 15 feet, so now you have a seam, and you are buying a 100-foot roll of tape and a gallon of glue for a 16-foot joint. The material is $6.21 a foot and the ceiling drops to 43.6%. You took a bigger job and made less on it. Fifty more square feet cost you 3.4 points.

And that is before the turf itself. The sheet prices the turf on the square feet laid, on purpose. In real life 250 square feet takes 2 full runs off the roll, 474 square feet bought to cover 250. Even the 1,500 square foot job cuts off 242 square feet. That offcut is not on this sheet. It gets its own episode.

200 square feet, one run, no seam
$5.83 a square foot of material, 47% ceiling
250 square feet, two runs, one seam
$6.21 a square foot of material, 43.6% ceiling
1,500 square feet, three runs, two seams
$5.01 a square foot of material, 54.5% ceiling
Turf comes 15 feet wide. Cross that line and you buy a roll of tape and a gallon of glue for one short seam.

Dye lot and direction

Here is one the sheet cannot price, and it can cost you more than any number on it. Turf comes in dye lots. Same manufacturer, same model, same everything, but a roll made in March and a roll made in June can come out a slightly different shade. Nobody notices a dye lot in a photo. Everybody notices it when two pieces are seamed side by side in the afternoon sun. So if you measure short and go back for one more roll, it may not match what is already installed. Front yard against back yard, you will probably get away with it. Side by side across a seam, you will not.

And turf has a direction. The blades lean, and every strip has to run the same way. You cannot turn a piece 90 degrees to make it fit, even when the math works. Do it and there is a stripe you can see from the street. So measure it right, order it all at once, order it from one lot, and put the waste in that order. Not because waste is good. Because a second order might not match. That is not a line on the sheet. It is the reason every line on the sheet has to be right the first time.

Where it goes wrong on your job

The 30 square feet an hour was measured on a clean, prepped 1,500 square foot yard, and nothing about your site is in it. These are the jobs that miss it. The site prep went into the $11 because nobody wrote it as its own line, and the crew spent a day digging that the price never covered. The base, the barrier and the infill were never on the quote, because the quote said turf. The job was 250 square feet, priced like 200, and the seam, the tape and the glue came out of the margin. The yard got measured short, the second roll came from a different lot, and the seam shows. A piece got turned to save a cut. The infill was an antimicrobial product at 4 times the price of sand, and the estimate still carried sand.

One job under budget usually has a story like one of those behind it. Write it down and move on. Five jobs under with no story means one of the inputs is wrong: the stack, the pace, or what you are paying for turf. On turf, check the stack first. It is the most likely line to be missing from the quote.

What to do with this

Take the last turf quote you sent and list every material that went into the job, not just the turf. Base, barrier, infill, tape, glue, nails. Divide each by the square feet, add them up, and divide the total by your price. That is your ceiling, in 10 minutes, before anybody swings a hammer. Then check one thing on the next small job: is any side longer than 15 feet? If the number surprises you, watch the episode and run your own sheet. If it doesn't, you have lost 10 minutes.