How to price a segmental retaining wall by the linear foot

A 24-inch dry-stack wall is $45.52 a foot of material, 34 cents off the mortared wall. At $150 a foot and 0.95 man-hours it makes 50%.

By Edgar Galindo · November 23, 2026 · EP 08 Segmental Retaining Wall of Are You Pricing This Right?

Watch the episode and get the sheets

This is a dry-stack retaining wall. It has no footer, no mortar, no grout, no rebar and no dampproofing. It is 6 lines of material, and you can build it with a rake and a level. On a wall like this, 2 heights matter. One is where you need a permit and an engineer. The other is where the block stops holding itself up and needs geogrid. Most people treat those as 2 problems at 2 heights. They are the same line, at about 4 feet, and you cross both in the same afternoon. So the dry-stack wall you can build without a stamp or a structural system shows about 24 inches. That is the wall this page prices: 24 inches showing, 50 feet long, $150 a linear foot. It is the mortared block wall from the last episode, built in segmental units. The material comes out 34 cents apart. The labor does not, and that is the story.

The numbers this sheet uses

These are mine, verified in September 2026. The block price matters most, because there are a lot of these blocks and they are not close in price. Get your own quote. Here 24 inches of wall show and 8 are buried, so 32 inches get built. Under that sits a 6-inch leveling pad. One caution before any of this: the permit rules are your city's. In many cities the 4 feet is measured from the bottom of the leveling pad to the top of the wall. Some measure only the face you can see. Check with your city before you quote a wall as work that needs no engineer.

Sell price to the customer
$150 a linear foot of wall
The wall
24 inches showing, 8 buried, 32 built, 50 feet long
Under the wall
a 6-inch compacted leveling pad
Bottom of pad to top of wall
38 inches, under the 48
The block
$10 a square foot of face, a realistic middle
What the crew is paid
$23 an hour, average
The burden
1.35
What an hour of labor costs
$31, the wage times the burden
The pace
0.95 man-hours a foot, pad through backfill, a crew of 3 by hand

2 lines at the same height

The first line is the permit. On a mortared block wall, in a lot of cities, it is 4 feet from the bottom of the footing. A dry-stack wall has no footer. It sits on a compacted leveling pad, and the same rule runs from the bottom of that pad. Add it up. 24 inches showing, 8 inches of buried course and 6 inches of pad is 38 inches. That is under 48.

The second line is the one nobody tells you about. Dry-stack block holds itself up by its own weight, and that is called a gravity wall. Depending on how deep and heavy your unit is, it runs out somewhere around 3 to 4 feet. Above that, the block alone cannot hold the soil, and you need geogrid. Geogrid is layers of structural fabric that run back into the soil. They turn the dirt behind the wall into part of the wall.

So the height where you need an engineer and the height where you need grid land on top of each other. Build taller and you cross both at once. You buy a structural system and a stamped design on the same day.

The permit line and the geogrid line land at about 4 feet. Build taller and you cross both on the same day.

6 lines, 4 units

There are 6 lines on this wall and 4 kinds of unit. Watch what each one is bought by, because that is the finding.

The leveling pad is bought by the linear foot. It is 6 inches of 3/4-inch crushed limestone base, compacted in 2 lifts. It runs 24 inches wide, about twice the depth of the block, so it extends 6 inches past the block on both sides. It is $2.22 a foot.

The block is bought by the square foot of built face. I am using $10 a square foot. I have seen premium block at the big-box store north of $24, and contractor structural block at $8. I picked $10 as a realistic middle, so use yours. My $10 matters less than where it goes. The wall is 32 inches built, 2.67 square feet of face for every linear foot, so the block is $26.67 a foot.

The cap is bought by the linear foot again. The cap unit and the construction adhesive are $5.15 a foot. Notice the unit just changed. The block is bought by the square foot and the cap by the foot, because a cap does not care how tall the wall is.

The core and drainage fill is bought by the cubic foot: number 57 washed stone at $2.30, 3.33 cubic feet a foot, $7.65. Drainage is 4-inch perforated pipe, 4-ounce non-woven fabric and fittings, $3.83 a foot. That is the same as the mortared wall, because the water does not care what the wall is made of.

Geogrid is bought by the square foot of grid, at 21 cents, and this wall is under the gravity line, so it needs none. The line still goes on the sheet, because you should always know whether the answer is zero or whether you forgot. Add the 6 lines and the material is $45.52 a linear foot.

1. Leveling pad, 3/4-inch crushed base, by the linear foot
$2.22
2. Block, $10 a square foot of built face times 2.67
$26.67
3. Cap and adhesive, by the linear foot
$5.15
4. Core and drainage fill, number 57 washed stone, $2.30 a cubic foot times 3.33
$7.65
5. Drainage, pipe, fabric and fittings, by the linear foot
$3.83
6. Geogrid, 21 cents a square foot of grid, none on this wall
$0.00
The wall, a linear foot of material
$45.52

The pad is the wall

Be specific about the pad material, because there are 2 schools. Crushed base has fines in it. It compacts to a firm platform and screeds dead level. Open-graded washed stone drains better, but it will not hold a screed.

On a dry-stack wall the base course is the wall, and there is no mortar to fix it later. That is why I use base. If you use base too, put the drain pipe at or below pad level. That gives the pad somewhere to send water, instead of holding it against the bottom course.

The stone that goes missing

Here is the line that goes missing on almost every segmental wall quote I have seen. Most retaining wall block is hollow. The masonry standard calls for at least 1 cubic foot of clean drainage stone for every square foot of wall face. That stone goes in 2 places: inside the cores of the block, and in a 12-inch zone behind it.

It has to be number 57 washed limestone. That is angular, crushed stone with no fines. Pea gravel is round, flex base is full of fines, and neither one belongs here. The stone costs $2.30 a cubic foot. The sheet carries 3.33 cubic feet for every foot of wall, which is $7.65 a foot. On 50 feet, that is about $400 of rock.

And it is invisible. You cannot see it when the wall is done, and nobody has ever asked me about it. Skip it and you have built a dam instead of a wall. Forget to quote it and you bought $400 of stone with your own money. On the mortared wall, the line that went missing was the grout. Here it is the stone. Both are the line you cannot see once the wall is up.

Core fill is $7.65 a foot, about $400 of stone on 50 feet. It is the line that goes missing from the quote.

3 lines do not care how tall the wall is

Look at what each line is bought by again, because the pattern is worth more than any single number on the page. 3 of the 6 lines are bought by the linear foot: the pad, the cap and the drainage. $2.22, $5.15 and $3.83 add up to $11.20 a foot. It is $11.20 at every height you will ever build. A 6-inch garden wall and a 4-foot wall pay exactly the same.

The block and the core fill scale with the face you build. Together they cost $12.87 for every square foot of built wall. The 6th line, the geogrid, stays at zero until the wall passes the gravity limit.

So the whole wall collapses into one line: $11.20 a foot, plus $12.87 per square foot of built face. Run it at 32 inches built, 2.67 square feet a foot, and you get $45.52, dead on. That is your price book entry. It is one formula for any height, until you cross the gravity limit and grid shows up. It works because it is built on what each line is measured in. A bucket like "small wall" or "big wall" knows none of that.

Bought by the linear foot: pad, cap and drainage
$11.20 a foot, at every height
Bought by the built face: block and core fill
$12.87 a square foot of built face
At 32 inches built, 2.67 square feet a foot
$45.52 a linear foot
Price a dry-stack wall at $11.20 a foot plus $12.87 a square foot of built face, at any height under the gravity line.

You build more than you sell

The $45.52 sits behind a face 2 feet tall. You sold 2 square feet of face for every foot, so the material is $22.76 a square foot. That is the number most people quote off.

But you sold 24 inches and built 32, because 8 inches is buried below grade. That buried course is real block, real setting time and real core fill, and none of it is on the invoice. You built 133% of what you sold. On an 8-inch garden wall you still bury 8 inches, so you build 200%. That is twice the wall for one price. It is also why the formula above runs on built face. You pay for the face you build.

Material, a square foot of face sold
$22.76
24 inches showing, 32 built
133% of what you sold
8 inches showing, 16 built
200%

What the price buys in hours

On a wall, labor is the hard part to estimate, so run it backward. Start with the price and the margin you want, take out the material, and see how much crew time is left. At $150 a foot and a 40% gross margin, you keep $60 and $90 is left to build the wall. Take out the $45.52 of material and $44.48 is left for labor. At $31 an hour, that buys 1.43 man-hours a foot, an hour and 26 minutes. A man-hour is one person working one hour.

At 45%, the same math leaves $36.98 for labor, 1.19 man-hours, an hour and 11 minutes. At 50%, it leaves $29.48, which is 0.95 man-hours, 57 minutes. All of this is gross margin. It is what is left after the material and the crew, before overhead. Gross profit is not profit.

The grid on sheet 3 runs the same math at other prices. At $110 a foot and 40%, the crew gets 0.66 man-hours, 40 minutes. In those 40 minutes they do the pad, the base course and 4 courses of block. Then the cap, the core fill, the pipe, the fabric and the backfill. Nobody builds a foot of wall in 40 minutes. At $130, 40% leaves 1.05 man-hours, about an hour and 3 minutes. $110 gets you nothing worth having.

$150 a foot at 40%
1.43 man-hours a foot, 86 minutes
$150 a foot at 45%
1.19 man-hours a foot, 71 minutes
$150 a foot at 50%
0.95 man-hours a foot, 57 minutes, what a real crew runs
$130 a foot at 40%
1.05 man-hours a foot, 63 minutes
$110 a foot at 40%
0.66 man-hours a foot, 40 minutes, not a real pace
At $150 a foot, a 40% gross margin buys 1.43 man-hours a foot. A 50% gross margin buys 0.95, which is 57 minutes.

What a real crew does

The crew rakes and compacts the pad, sets the base course dead level, stacks, caps, fills the cores, lays the pipe and fabric, and backfills. There is no concrete to wait on, and no mortar, grout or dampproofing. Call it 0.95 man-hours a linear foot. That is 57 minutes of one person for every foot of wall.

Published cost data has this wall at about 0.6 man-hours a foot, 36 minutes. That figure has a skid steer feeding block to the crew, and a plate compactor that shows up at 8 and leaves at 4. Mine is 3 people, a wheelbarrow and a rental picked up on the way in. Crews with a machine report 0.3 to 0.5 a foot all-in, 18 to 30 minutes. So 0.95 is the ceiling without a machine, and most of you do not have the machine. With it on the job, you are nearer 0.6 and the sheet gets better.

These labor figures are estimates, and they carry the conclusion. At 0.95 the labor is $29.45 a foot. With the $45.52 of material, the foot costs $74.97. At $150 you keep $75.03, a 50% gross margin. The price for exactly 50% is $149.94. You are 6 cents off the line. That is either very satisfying or slightly alarming, depending on whether you meant to be there.

At a real 0.95 man-hours a foot, $150 holds a 50% gross margin. The price for 50% is $149.94, 6 cents off the line.

The levers, and why speed got weaker

There are 3 ways to make more money on this wall. Move each one by 10% and see what you get. A 10% higher price is $165 instead of $150, which is $15 more a foot. Material 10% cheaper is worth $4.55 a foot. A crew 10% faster is worth $2.95.

That is $15 against $2.95. Price beats speed 5 to 1. To match the price move on speed alone, the crew would have to get 51% faster. To match it on material, the material would have to be 33% cheaper. This is the 7th episode with levers in it, and the 7th time the same answer. Price beats a cost line by your price divided by that line. Here, $150 over $29.45 of labor is 5.1.

Here is what is different about this one, and it surprised me. On segmental, speed is a weaker lever than on the mortared wall. On the CMU wall, price beat speed 3.7 to 1, and matching a price rise took a crew 37% faster. Here it is 5.1 to 1, and it takes 51%.

The reason is that you already banked the speed. Going dry-stack took the labor from $40.30 a foot down to $29.45. That was the productivity win, and it was a big one. Once you take it, there is less labor left in the job to squeeze, so squeezing gets you even less. Pick the faster system, then stop chasing speed. From there, it is your price.

10% more price
$15.00 a foot
10% cheaper material
$4.55 a foot
10% faster crew
$2.95 a foot
Faster crew it takes to match the price move
51% here, 37% on the CMU wall
Price over labor
5.1 here, 3.7 on the CMU wall
Price beats speed 5 to 1 on this wall. Dry-stack already banked the speed: $40.30 of labor down to $29.45.

The leftover roll

This one has nothing to do with this wall. It shows up the moment you go taller and need grid. Grid is cheap, at 21 cents a square foot. A 40-inch wall that is 50 feet long needs about 840 square feet of it. That is $176 for the whole wall.

The problem is that grid comes in rolls. A roll is 1,800 square feet and about $375. So you buy $375 worth and install $176 worth. I priced it at what I install, which is $3.53 a linear foot. That is the right way to do it, if you are going to use the rest.

So ask yourself how many walls a year you build that need grid. If it is 6, that leftover roll is inventory. It gets used next month, and it cost you nothing. Now say this is the only reinforced wall you touch all year. That other $200 of grid sits in your shop until it is brittle. Your real cost was $7.50 a foot, and you priced $3.53. You paid double and priced single.

Every leftover is inventory or waste, depending on how often you do the work. Half a roll of weed barrier in the trailer is free if you are laying turf next week. If you are not, it is money. It is the same roll in the same trailer with a different answer, and only you know which one it is.

One product note. There is a cheap grid at the big-box store, in the paver aisle, called biaxial. It is a paver base product, strong in 2 directions instead of very strong in 1. Nobody has tested how it connects to your block. Structural grid is uniaxial. If you are buying grid off a shelf with no spec sheet, you are not buying structural grid.

Every leftover is inventory or waste, depending on how often you do the work. Grid priced at $3.53 a foot can really cost $7.50.

Against the mortared block wall

I priced this exact wall in mortared CMU in the last episode, with a poured footer, mortar, grout, rebar and dampproofing. The material on that wall is $45.86 a foot. The material here is $45.52. That is 34 cents apart. One of them has a poured concrete footing, mortar, grout, vertical steel and a waterproofing system. The other is stacked block and gravel. In material, they are the same wall.

The labor is where they split. The CMU wall takes 1.3 man-hours a foot, an hour and 18 minutes. This one takes 0.95. That is $10.85 a foot more labor on the CMU wall. At $150 a foot, it is a 42.6% gross margin against 50%. That is 7.5 points of gross margin, and not $1 of it is material.

Which means most people pick between these 2 walls backwards. They pick on looks, on what the supplier had, or on what they built last time. It is a labor decision wearing a material costume. Find out what every line is bought by, add it up, and then compare the systems on what really differs. On these 2 walls, that is the labor.

Material, a linear foot
CMU $45.86, segmental $45.52
Man-hours, a linear foot
CMU 1.30, segmental 0.95
Labor, a linear foot at $31 an hour
CMU $40.30, segmental $29.45
Gross margin at $150 a foot
CMU 42.6%, segmental 50.0%
The 2 walls are 34 cents apart in material and 7.5 points apart in gross margin. All of the gap is labor.

Where it goes wrong on your job

The 0.95 is a crew of 3 by hand, and nothing about your site is in it. These are the jobs that miss it. The budget came out of a book at 0.6, with no skid steer on the job. The core fill was never on the quote, and the wall was short $7.65 a foot before the crew arrived. The pad was washed stone, it would not hold a screed, and the base course went down out of level. On a dry-stack wall there is no mortar to fix that later. The pipe sat above the pad, so the pad held water against the bottom course. The quote priced 24 inches of face and the crew built 32. The block price was a guess, on a product that runs from $8 to more than $24 a square foot. The customer asked for a taller wall, and nobody checked it against the gravity line and the permit line.

A job over budget usually has a story like one of those behind it. Write it down and move on. 5 jobs over with no story is your real pace. Then 1 of 3 numbers has to move: the price, the pace, or the material on the quote. On a dry-stack wall, check the quote for the core fill first. It is the line that goes missing.

What to do with this

Take the last dry-stack wall you quoted. Find the core fill on it. If it is not there, that is $7.65 a foot on a 24-inch wall. Then get a real quote on the block you use, because that single number decides whether any of this holds. Measure the next wall the way your city does, and see where it lands against 48 inches and the gravity line. Then take the crew hours on the last wall from your foreman, divide by the feet, and find that row on sheet 3. The free calculator runs the same numbers, with tabs for the levers, the leftover roll and this wall against CMU. If the number surprises you, watch the episode and run your own sheet. If it does not, you have lost 10 minutes.

Ledge is landscape design-build software. These sheets are the thinking underneath it.